KP Energy Commissions 23 MW Wind Power Project in Gujarat

KP Energy informed the exchange that it had successfully commissioned further 23.1MW (Phase-X) ISTS connected Wind Power Project comprising 11 numbers of Wind Turbine Generatorss of 2.1MW each at the Sidhpur site in Devbhoomi Dwarka in Gujarat.

This Phase-X commissioning is a part of the 250.8MW ISTS connected Wind Power Project capacity awarded to Apraava Energy Private Limited by Solar Energy Corporation of India Limited (SECI) under Tranche-VIII bidding.

KP Energy is developing the Project for Apraava Energy Private Limited as a Contractor under the Land and Balance of Plant Contract.

With the present Phase-X commissioning, the net cumulative capacity commissioned at Sidhpur site stands at 245.7MW (i.e., 52.5MW + 29.4MW + 25.2MW + 21MW+ 10.5MW + 25.2MW + 29.4MW + 16.8MW + 12.6MW + 23.1MW) against the awarded capacity of 250.8MW.